photo: nationalgallery.sg

Based on the Auditor-General’s Office (AGO) latest report, it found multiple weaknesses in the financial governance of the National Gallery development project which “did not give assurance that public funds has been properly managed”.
The report was made public today (16 July), following the AGO’s audit of government accounts for the 2018/2019 financial year.
The National Gallery development project is a project completed in 2015 within the approved budget of S$532 million under the Ministry of Culture, Community and Youth (MCCY), and is managed by the National Gallery Singapore (NGS) through a Funding Agreement (FA).
“AGO’s test checks revealed weaknesses such as waivers of contractual provisions involving $13 million without due scrutiny by MCCY, and inadequate monitoring (including the lack of timely audits) to ensure that the final sum to be paid for the main construction contract was properly supported,” said the report.
AGO pointed out that the FA didn’t detail out who is supposed to approve waivers of contractual provisions. If that is not all, “MCCY did not explicitly give authority to NGS to decide on such waivers”.
Despite not gaining approval, AGO stated that NGS went on without due scrutiny by MCCY.
In addition, AGO noted that the Ministry only questioned NGS regarding the waivers in September 2018, one year after the construction contract has been issued and the final payment has been made.
Apart from that, there was no adequate monitoring mechanism placed by the Ministry to ensure “that the waivers with substantial financial implications were highlighted for its attention on a timely basis”.
Besides that, the report also mentioned that there was “a significant gap” between the last monthly status report and the last audit of the project expenditure. In fact, the Ministry only scheduled the final audit in the second half of 2018, which is close to a year after the final account was given and the payments were made. It also noted that it was not aware of the waivers granted until a year after all the accounts were issued and payments settled.
“The waivers of contractual provisions had significant financial implications amounting to $13 million. There is hence a need for MCCY to strengthen its oversight to ensure financial prudence in the use of public funds managed by NGS on its behalf,” the report stated.
As such, AGO felt that MCCY should have had a “proper governance framework and key controls” of the National Gallery development project, given that it is the owner of NGS.
“These include ensuring that the FA sets out clear roles and responsibilities of NGS and its Board, and that decisions involving large sums of public funds are made only after obtaining MCCY’s approval,” it added.
In response, the Ministry said that despite the challenges to re-develop two gazetted national monuments and unique requirements of an art infrastructure, NGS still managed to complete the project within the time frame and approved budget. However, both MCCY and NGS agree that the processes can be improved.

Insufficient oversight in management of contract variations

There were also lapses found in the main construction contract, exhibition fit-out contracts and integrated consultancy services contract in the National Gallery Development project, AGO said. The total value of the contracts amounted to S$458.98 million.
Some of the lapses include not obtained approvals before contract variations were carried out, approval obtained from incorrect approving authority and failure to deduct costs for incomplete works, among others.
Out of the 403 contract variations checked, AGO found that there were lapses in the approval of 142 variations amounting to S$12.4 million.
“AGO also found two instances under the main construction contract where works provided for in the contract were not carried out. Contract variations should have been issued to deduct the costs from the contract sum. However, this was not done, resulting in an estimated overpayment of $11,500,” the report revealed.
It added that in total, the estimated overpayment for works not done was S$265,800.
As such, AGO explained that in order for financial prudence and discipline to be maintained, it is crucial for approvals to be obtained from the right authorities and costs deduction for incomplete works must be done to gain full value for the public funds spent

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

Why is our government treating us like the enemy?

By Jentrified Citizen Like many fellow Singaporeans I am outraged and deeply…

骇客入侵WhatsApp置入监控软件 用户受促更新

社交通讯软件WhatsApp公司在周一(13日)证实遭骇客入侵,骇客利用WhatsApp的语音通话功能置入监控软件,至今未知有多少人受影响。 WhatsApp在全球有15亿用户,该公司已呼吁用户立即更新程式。 据《金融时报》报导,攻击软件是由以色列软件制造商NSO集团开发,该公司的旗舰软体“Pegasus”可透过麦克风及摄影机,从目标装置搜集个人资料。 NSO集团的软件被指多次被利用来针对记者、律师、维权人士和异议分子。 即使用家不接电话,软件也会被自动安装,且电话纪录亦会被删除,意味骇客可在用户完全不知情的情况下入侵手机,进行监控。 WhatsApp的安全团队月初发现漏洞,增强语音通话的保安措施,并在上周推出修补程式,周一再敦促用户更新。 WhatsApp也针对被骇事件,通报人权组织和美国司法部。 至于NSO集团则回应,该公司的技术仅授权政府用于打击犯罪和恐怖活动,指该公司不会自行操作该系统来针对个人或机构,若警调查发现不当使用会采取行动,甚至关闭有关系统。 国际特赦组织其中一名职员在去年也申诉遭有关软件监控,该组织表示有意参与法律援助以对以色列国防部施压,要求吊销NSO集团出口执照。    

Tan Wah Piow to AGC: Phey ‘s criminality is more than adequate in law to render 1975 conviction unsafe

Singapore exile and lawyer, Tan Wah Piow has just replied to Attorney-General’s…

“山寨版”官方打假账号? 通讯新闻部:“FActually”非官方脸书专页

为了厘清坊间流言和澄清事实,政府官网gov.sg有个名为Factually网页链接。不过通讯与新闻部澄清,在脸书上的“ FActually Singapore”,并不是官方的脸书专页。 如果浏览“FActually Singapore”的脸书和Instagram账号,可能让民众误以为这是官方在社交媒体的账号: 内容宣扬和转发政府政策 不过若仔细浏览其内文,行文和处理报导的方式,都会令人质疑这是否是隶属于官方的账号。不过一些内容则赞扬一些官方政策,或是转发官方资讯等。充其量是个亲政府的粉丝专页。 而本社记者也向通讯与新闻部求证,有关专页是否是官方经营的账号,后者也证实,不论是“FActually Singapore”的社交媒体账号,都不是官方经营的。 新加坡商号进军中国也被山寨 这也让小编想起在中国常出现各种玩弄字母的山寨仿冒商号或品牌,例如最近竟冒出名为“Cherlss & Keich”的山寨品牌,让人误以为是正版新加坡时尚名牌“Charles…