Further delays are to be expected regarding the JB-Singapore RTS Link project as Singapore’s Ministry of Transport (MOT) announced on Thu (4 Apr) that a review of the bilateral agreement (BA) regarding the project is “possible”.

MOT noted that any review or deadline extension will be “subject to mutual consent of both countries”.

“For example, Malaysia can request to suspend the RTS Link Project, as was done for the Kuala Lumpur-Singapore High Speed Rail Project.

“Alternatively, Malaysia can terminate the existing RTS Link BA and request to negotiate a fresh BA with Singapore,” added MOT.

The Ministry’s statement is a response to Malaysia’s request at the end of last month to extend the deadline of the project by six months in order to leave room for a review of the RTS Link project’s “scope, structure and costs previously agreed between the two countries”.

Acting Minister for Transport Vivian Balakrishnan told Parliament last month on 7 Mar that the RTS link project between Bukit Chagar in Johor Baru and Woodlands North station on Singapore’s Thomson-East Coast MRT Line is “no longer on track” contrary to its original scheduled operations start date on 31 Dec 2024.

His statement was made in response to Jurong GRC Member of Parliament Ang Wei Neng’s question regarding the status of the project during a parliamentary debate on MOT’s budget.

TODAY reported that the deadline has already been shifted four times previously, namely “from last June to September, then to two dates in December before settling on Feb 28”.

The formation of a joint venture company by Singapore’s SMRT and Malaysia’s public transportation company Prasarana Malaysia Berhad was slated to take place in June last year, TODAY observed.

However, Malaysia had plans to replace Prasarana, which leaves the concession agreement between Singapore’s Land Transport Authority and its Malaysian counterpart, which was meant to be signed by 30 Sep last year, hanging.

“In the spirit of bilateral cooperation, Singapore has been willing to engage Malaysia on its proposals for Malaysia’s joint venture (JV) partner for the RTS Link OpCo,” said Dr Balakrishnan.

“Unfortunately, Malaysia has repeatedly delayed confirming its JV partner,” he added.

In January, Transport Minister Khaw Boon Wan said in a written response to a parliamentary question from Mr Ang that the project was “not progressing well” as “milestones have been missed”.

The Edge Markets reported earlier this month that the Malaysian government was seeking, for the fifth time, an additional six-month extension in order to have more time to decide on its next course of action.

Malaysia’s Transport Minister Anthony Loke told reporters: “We are asking for more time from the Singapore government, for us to study the other options.

“Of course, we are looking at the costs of the project, how we can reduce the costs further and how do we utilise the project,” he added.

When asked if the Singapore government has given consent to the extension, Loke said: “There will be some agreement with them [the Singapore government]. We will reveal [the details] later.”

The Star Online quoted Loke as saying on 12 Mar that RM4bil (S$1.3bil) out of the RM10bil (S$3.3bil) cost for the project will be borne by Malaysia.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

6-year-old child traumatised to attend school in Kelantan, allegedly bitten on lips by male teacher

A shocking revelation emerged when a parent discovered that her six-year-old son’s sullen behavior stemmed from alleged abuse by his male teacher, who bit his lips, ears, and nose. The child even described the teacher’s teeth as “yellow and his mouth as black,” which made him feel traumatised. The Malaysian Ministry of Education is currently investigating the matter and will respond accordingly if the allegations are substantiated.

Opposition accused DAP Chairman Lim Guan Eng of fearmongering voters against ‘green wave’

Opposition leaders in Malaysia have accused Lim Guan Eng, the chairman of the Democratic Action Party (DAP), of deliberately addressing sensitive 3R issues (Rulers, race, religion) in a Mandarin speech. Allegedly, he stated that if the “green wave” dislikes certain temples, they might attempt to demolish them. In response, Mr. Lim clarified that his statements were misrepresented by a news portal. Nevertheless, the former Finance Minister assured his full cooperation with the police in the ongoing investigation.

Worldwide donors raised RM1.2 million within 29 hours to save 670g premature Malaysian baby born in S’pore

Nearly 15,000 donors around the world have raised RM1.2 million to save…

LTA: No changes to ERP rates for the 4th quarter of 2016

The Land Transport Authority (LTA) has announced on Monday (31 October) that there…