In its audit report for Financial Year 2015/2016 published on 26 July, the Auditor-General Office (AGO) found that found that the Ministry of Manpower (MOM) bought a computer system, a Document Generator System (DGS), for a sum of $432,407 for integration with its Foreign Domestic Worker System (FDWS) only to find that it could not be integrated.

AGO states that the DGS had been left unused since November 2014, for one and a half years as at the time of audit. This has resulted in a waste of public funds, said AGO.

In its test-check on assets purchased by MOM for its FDWS (costing $27.49 million), including the DGS, AGO noted that MOM had not carried out a robust evaluation before proceeding with the procurement of the DGS.

AGO noted that MOM, in its tender evaluation in March 2014, did not evaluate whether the DGS could integrate with the FDWS which was to be developed separately.

According to MOM, it decided not to use the DGS after it found out that the DGS could not be integrated with the FDWS in November 2014 as it would not be cost effective to make the required modifications.

However, AGO noted that there was no documentary evidence that MOM had put up any plans to redeploy the unused DGS assets. There were only some working level discussions on the redeployment, which eventually did not materialise.

AGO notes that a number of the DGS assets (such as hardware servers, database licences) could have been redeployed for other uses within MOM or other government agencies. Not doing so would result in a waste of public funds as the usability of these assets would be reduced with the lapse of time, due to technology obsolescence or expiry of licences.

It is said that MOM acknowledged that its evaluation should have been more robust and that it could have taken more active steps to explore redeployment of the DGS assets to other government agencies. MOM informed AGO that it is currently exploring the redeployment of the DGS assets within MOM.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

过去三年 客工宿舍经营者每年违规近80例!

人力部指出,过去三年来,客工宿舍经营者涉及抵触宿舍管理法规,每年竟可多达80例! 据人力部回应亚洲电视台的询问,指出其中60巴仙都属“轻微疏失”,例如未能维持宿舍内的整洁等等。 上月5日,人力部长杨莉明曾在国会指出,每年平均有1200名雇主,因没为客工安排适当住宿而被惩处;还有20名宿舍经营者,因触犯《外籍员工宿舍法令》被惩处。 而我国有43座在上述法令管制下的大型客工宿舍。这意味着有近半的经营者都曾涉及违规。 人力部称,即便轻微违规当局仍会采取行动,涉及违规的经营者,将被要求立即纠正,直至人力部满意为止。 根据《外籍员工宿舍法令》,若出现违规行为,宿舍经营者可被罚款最高5万元,监禁一年或两者兼施。 不过,若出现屡犯不改或严重疏失,人力部则会提控有关经营者,例如2019年,MES集团的子公司Labourtel Management Corporation及其公司董事Parvis Ahamed Mohamed Ghouse,被控上庭。

Rampant job ads looking for “skilled” foreign workers paying below minimum EP/SP salary

A TOC article (‘F&B group founded by award winning entrepreneur, caught for…

Singaporean spots state flag in bin, removes it and educates cleaner on proper handling

Sathiyaselan Sivalingam was surprised when he saw the Singapore flag sticking out of a…

部分大型基建工程近年出现成本超支

在本月11日,《海峡时报》一篇用户付费文章揭露,地铁环线延长线第六阶段(Circle Line 6,或简称CCL6),预计总耗资48.5亿新元。 CCL6总长约四公里,增设三站连接滨海湾站和港湾站。这意味着,每公里的成本就达到12亿元,是首五阶段平均成本的五倍。根据2017年4月的《联合早报》报导,当时工程预计耗资37亿元,成本足足增涨了11.5亿元。 陆路交通管理局(LTA)针对《海时》提问指出,成本高涨基于数项因素,包括地下建设工程的挑战和复杂程度,以及必须设法与现有运作中的首五期环线互相整合。 陆交局也指出,通膨也是其中一项因素。总长33公里的首五期环线是在20年前开始的,当时的价格成本较低。 其实近年来,也可见许多在本土施工的基本设施,最终成本远高于预期。 滨海沿海高速公路(Marina Coastal Expressway) 举例2007年,政府批准陆交局以25亿元的成本,兴建五公里长的滨海沿海高速公路。 当时,政府相信该高速公路能应付滨海湾区域密集发展而增长的交通流量,同时也作为滨海湾与全岛其他区域连接的主要干线。…