Singapore
North East Line renewal works progressing, full completion expected by early 2026
Transport Minister Chee Hong Tat confirmed that the North East Line (NEL) renewal project is progressing, with completion expected by early 2026. While major system upgrades were completed in 2021, train refurbishments were delayed due to COVID-19. Of 25 first-generation trains, 16 have been upgraded, with the rest entering service in phases.

Transport Minister Chee Hong Tat has confirmed that the North East Line (NEL) renewal project is making steady progress, with completion now expected in the first quarter of 2026.
While major system upgrades were finished in 2021, the refurbishment of first-generation trains has been delayed due to the COVID-19 pandemic.
This was said in response to Workers’ Party Member of Parliament Dennis Tan Lip Fong, who raised a parliamentary question on 28 February seeking an update on the renewal project.
He also inquired about the long-term sustainability of the NEL after the current renewal works.
The Land Transport Authority (LTA) and SBS Transit (SBST) began the renewal works in 2019, focusing on refurbishing 25 first-generation trains and upgrading key infrastructure, including track, power, signalling, and platform screen doors (PSD).
As of January 2025, 16 trains have been successfully refurbished and deployed for passenger service. The remaining nine will be progressively put into service by early 2026.
These upgrades aim to enhance the commuter experience and improve service reliability.
The refurbishment includes replacing critical electrical and mechanical components, upgrading air-conditioning and ventilation systems, and refreshing train interiors with new seats, panels, and flooring.
Additionally, passenger information systems have been enhanced, and condition monitoring systems are being installed to better track train performance and optimise maintenance.
The project was originally scheduled for completion by the third quarter of 2024, but the refurbishment of trains faced delays due to global supply chain disruptions during the pandemic.
The Ministry of Transport (MOT) had previously addressed this delay in a 2022 parliamentary response.
Minister Chee reassured Parliament that these upgrades would extend the lifespan of the NEL and enhance service reliability for years to come. However, as with all rail systems, further renewal works will eventually be required as part of ongoing maintenance and modernisation efforts.







