In July 2017, the Ministry of Home Affair (MHA) put out a tender for a shipbuilding project for the Police Coast Guard (PCG).

The tender called for a firm order of the construction of 12 patrol boats with the option to supply and deliver a further five boats. It also called for maintenance of the boats for a firm period of 15 years with the options to extend for another three years.

MHA decided to award the tender to a company called ST Marine, the marine arm of defence and engineering group Singapore Technologies Engineering (STE). Temasek Holdings is the controlling shareholder of STE.

The GeBiz document that TOC obtained showed that ST Marine was competing against at least five other shipbuilders – Damen Shipyards, Lung Teh Shipbuilding, Naval Group Far East, Odyssey Marine, and Strategic Marine. GeBiz is the government’s e-procurement portal where suppliers bid on tenders posted by the government.

According to Business Times, this tender is ST Marine’s most significant shipbuilding contract win in months. Back in December 2016, ST Marine won a contract via joint bid with Penguin International to supply three reserve vessels, two small aluminium boats and one heavy marine fire vessel for the Civil Defence Force. Penguin International undertook the construction of the aluminium boats while ST Marine handled the steel vessels.

For this project with the Police Coast Guard, TOC understands that Penguin International had intended to participate in the tender process but they were dropped due to late submission.

BT’s source noted that this new contract with the PCG will see ST Marine build aluminium boats for the first time in years.

The tender process for this new contract begun in July 2017 and closed in November that same year. The bidders were only notified that the contract had already been awarded when the automatic system notification from GeBiz emailed them about the closure of the tender bid.

Now, according to the Government Procurement Regulation 2014, a contracting authority – in this case, MHA – has to publish a notice to announce that the contract has been awarded no later than 72 days after the award was given.

But in this case, MHA took much longer than the required 72 day period to notify the other bidders that the contract had already been awarded. In fact, the other suppliers were only notified more than 120 later. So why did it take so long for MHA to make the announcement given that the contract was awarded in July last year?

Not only that, there is also the curious case of the contract being awarded to ST Marine in the first place.

The project was estimated to be S$203.7 million according to MHA’s 2018 budget. However, ST Marine’s was awarded the contract with their bid of S$312.7 million – about 55% more than the estimated. In fact, BT had said in their article that the amount awarded to ST was ‘up to S$400 mil’. According to industry experts whom TOC spoke with, this is likely due to MHA taking up the option to purchase additional boats and extension of maintenance period.

Still, this begs the question of why MHA chose to award the contract to the Temasek-held company which has no recent experience in supplying aluminium boats and at an amount significantly higher than the original tender?

Damen Shipyards, Lung Teh Shipbuilding and Naval Group Far East are all established international shipbuilding companies with strong experience backing them up. Strategic Marine, a local shipyard, is also a well-established aluminium boat yard that has built a significant number of boats for PCGs before. Why were they passed over for ST Marine?

TOC has written to MHA for their comment on the tender award and to seek clarification on the progress of the project. As according to the project timeline, ST Marine should be well underway with construction. It’s possible that the significantly higher cost quoted by ST Marine is based on their ability to fulfill the order faster than the other suppliers said they could. But if that is not the case, then the basis for this tender award to ST Marine seems dubitable.

We have also reached out to the Auditor General’s Office and the Defence Science and Technology Agency which oversees GeBiz for their comments regarding the lapse of the 72-day time limit for the notice of award of contract.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

部分大型基建工程近年出现成本超支

在本月11日,《海峡时报》一篇用户付费文章揭露,地铁环线延长线第六阶段(Circle Line 6,或简称CCL6),预计总耗资48.5亿新元。 CCL6总长约四公里,增设三站连接滨海湾站和港湾站。这意味着,每公里的成本就达到12亿元,是首五阶段平均成本的五倍。根据2017年4月的《联合早报》报导,当时工程预计耗资37亿元,成本足足增涨了11.5亿元。 陆路交通管理局(LTA)针对《海时》提问指出,成本高涨基于数项因素,包括地下建设工程的挑战和复杂程度,以及必须设法与现有运作中的首五期环线互相整合。 陆交局也指出,通膨也是其中一项因素。总长33公里的首五期环线是在20年前开始的,当时的价格成本较低。 其实近年来,也可见许多在本土施工的基本设施,最终成本远高于预期。 滨海沿海高速公路(Marina Coastal Expressway) 举例2007年,政府批准陆交局以25亿元的成本,兴建五公里长的滨海沿海高速公路。 当时,政府相信该高速公路能应付滨海湾区域密集发展而增长的交通流量,同时也作为滨海湾与全岛其他区域连接的主要干线。…

受访者数度发飙走人 《纳吉之言》夺最佳访谈奖

马来西亚前首相拿督斯里纳吉在改朝换代后接受一项专访,在专访中数度发飙,甚至离席走人,这个专访赢得了2019年英国皇家电视协会电视新闻「年度最佳访谈」奖项。 纳吉是在2018年10月27日接受半岛电视台“101 east”的专访,主持人为半岛电视台记者玛丽安祖莉。 半岛电视台“101 east”宣布获奖消息时,也上载了当时的纳吉访谈,让民众能够重温。 在访谈中,玛丽安询问了纳吉有关一马公司、粉红钻石和蒙古女郎事件,更质问纳吉为什么当时将她驱逐出境,“我只是想了解真相”。 针对玛丽安的访问,纳吉刚开始还可以冷静回答,甚至数次要求玛丽安不要打断他的回答。但是随着问题也越来越尖锐,纳吉几乎失去冷静,更直言“不要再讲了,我受够了!”,“你这样对我不公平!” 纳吉曾经在访谈中一度起身要离开,他的新闻秘书拿督斯里东姑沙里夫丁也趋前安抚,玛丽安也表示将转移课题后,纳吉才重新回到座位上。但是,当玛丽安询问到刘特佐时,纳吉表示不能容忍,起身离开。 英国皇家电视协会新闻奖评审团指出,3名获得“年度最佳访谈”奖项提名者,都是采访者的典范。但是《马来西亚:纳吉之言》则因为勇气可嘉、坚持和纯粹,脱颖而出。 他们也表示,虽然访谈内容集中在一个课题上,但是并不能减损观众的理解能力,对受访者的唯利是图感到惊讶万分。

COVID-19: Netizens praise Malaysia for recording more recovered cases than new infected cases

On Thursday (9 April), Malaysia saw a sign of hope after it…

Roy Ngerng's sacking – "politically motivated"?

The employer of blogger Roy Ngerng, Tan Tock Seng Hospital (TTSH) announced…