In a report dated 3 July this year, the Auditor-General has revealed lapses in the spending of several ministries and government agencies, including, but not limited to, the Ministry of Defence (MINDEF), the Ministry of Education (MOE), and the People’s Association.

In the Auditor-General’s report, lapses were found in the spending under MOE.

Among them was the contract management of school development projects, in which MoE had engaged consultants to manage such projects.

Long delays in issuance of final accounts for all 30 school construction contracts, with final payments totalling up to $13.61 million, were part of the aforementioned lapses.

There were also cases where modifications to construction contracts were not properly managed, resulting in an estimated overpayment of S$154,900, said the AGO.

“Given these lapses, there was no assurance that MOE had exercised adequate oversight of its consultants on issuance of final accounts and management of contract variations as well as financial prudence in the use of public funds in these development projects,” it added.

In a statement on Tuesday, MOE said it is addressing the concerns raised by the AGO and is improving its internal processes, according to Channel NewsAsia.

“MOE acknowledges the importance of prompt issuance of final accounts in our school development projects. We are working with our consultants to issue the final accounts of all 14 outstanding contracts by end 2018,” it said.

The ministry is also recovering the overpayment of S$154,900 arising from contract variations, it said.

“Given these lapses, there was no assurance that MOE had exercised adequate oversight of its consultants on issuance of final accounts and management of contract variations as well as financial prudence in the use of public funds in these development projects,” it added.

In a statement on Tuesday, MOE said it is addressing the concerns raised by the AGO and is improving its internal processes.

“MOE acknowledges the importance of prompt issuance of final accounts in our school development projects. We are working with our consultants to issue the final accounts of all 14 outstanding contracts by end 2018,” it said.

The ministry is also recovering the overpayment of S$154,900 arising from contract variations, it said.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

Hundreds of S'poreans watch S'pore-banned film in M'sia

Despite being a working day, some 400 Singaporeans travelled across the border…

Use alternate sentence in place of death sentence

For Immediate Release The following is a joint Statement from the Think Centre, Singapore…

上演《速度与激情》?! 轿车卡在休旅车和路墩之间

这些驾驶者到底是怎么搞得,既然车子驾到另一辆车子上了??特技吗? 此意外于周一(5月25日)下午1时40分,在丽泉公寓(Seletaris Condominium)附近,朝向兀兰方向的甘巴士路(Gambas Road)上发生,所幸并没有接获任何伤亡事件。 视频所见,一辆车子被卡在了路墩和另一辆休旅车之间,呈半倾斜状态,看了不禁让人冒冷汗。 网友 Yusof将视频上传给脸书群组All Singapore Stuff后,吸引了众多网民观看,不少网民猜测意外是因为两辆车子的车主互不相让所致,有者则认为是前方的车子发生故障无法行驶时,后方的车子无法及时刹车,想转弯避开却又失败,才出现如此状况。 然而,不少网民也开玩笑地说道,“怎么没有做好安全距离?”、“上演速度与激情(Fast and Furious)吗?”、“有人表演特效”。