The Land Transport Authority (LTA) has issued a press release on Wednesday evening to address some of the issues relating to the 26 North-South and East-West Lines (NSEWL) trains that had defects found on them, emphasizing that the trains on NSEWL are safe for service.

It was earlier reported on Tuesday by FactWire, an investigative news agency that defective trains were secretly returned to CSR Sifang by SMRT without the public’s knowledge. The news agency verified and documented the transport of defective train carriages from the SMRT Bishan Deport to the port.

In its press release, LTA stated that it had awarded the contract, 151A in 2009 to Kawasaki Heavy Industries and CSR Sifang to design, manufacture, and deliver 35 new trains for the NSEWL. It added that the trains were progressively put into service from 11 February, following rigorous testing of their safety and reliability.

LTA described when and how the defects were found and the details of what will be done to rectify the defects. It also noted that the cost of shipping will be borne by the contractor.

However, LTA has yet to explain why this information was kept from the public until the report by FactWire was made this week.

Below is the actual text of the press release issued by LTA

Battery and Draughtscreen Issues

Prior to the commencement of passenger service, all new trains arriving in Singapore would be put through testing and commissioning. The same was done for the KHI-CSR Sifang trains. During such testing, there was an incident on one train where the cover of the train battery housing flew open due to a build-up of gases. The manufacturer took immediate action to replace its supplier and improved the design of the battery housing for all affected trains.

Incidents of cracks of the draughtscreen on five trains were also discovered. These were found to be caused by errors during the installation process and unrelated to the hairline cracks found on the 26 trains’ car-bodies.

It is not unusual to detect some defects on new trains.  We then take appropriate action to have them rectified by the manufacturer.

Hairline Cracks

In July 2013, during a routine inspection of the trains, hairline cracks on the surface of the car-body bolster were found. 22 of the 26 trains were in passenger service then. LTA immediately carried out further inspections. No cracks were found on other components of the trains.

Bolster Location
Bolster Location

Laboratory tests showed that these hairline cracks were due to localised impurity in the aluminium car-body material that occurred during the manufacturing process. LTA engineers and its contractor assessed that the hairline cracks would not affect the operational safety of the trains. To confirm this, LTA further sought the opinion of an independent third-party assessor, TUV Rheinland, which concurred that the trains were safe to operate.

Hairline crack on train bolster – 142mm in length (Photo - LTA)
Hairline crack on train bolster – 142mm in length (Photo – LTA)

Due to the nature of the defect, the most effective way of addressing it is to replace the entire car-body shell. As the trains were under warranty, we required the contractor to replace the entire car body shell. Hence, since July 2014, the affected trains have been progressively sent back to the factory for rectification works. The costs of the shipping are borne by the contractor.

To ensure that this unexpected occurrence did not affect our train deployment, LTA has been working closely with SMRT. The replacement of a train car body is time consuming and labour-intensive, with each car body replacement taking up to four months. Hence, to minimise the impact on our train operations in Singapore as well as the lack of facilities and space for repair works of this nature at our depots, only one train is sent back to the factory in China at any one time. We did not send all of the trains back at once as they were still fit and safe for service and we wanted to ensure sufficient train-availability for commuters.

Starting next year, with the arrival of more new trains for NSEWL and when trains currently undergoing resignalling are ready, LTA will be able to send two trains concurrently for replacement works. This will speed up the rectification programme and its completion can be brought forward to 2019.

As of today, the car-body replacement for five of the 26 trains has been completed. The car-body of the sixth train is being replaced. As per safety protocols, LTA, together with the contractor, will continue to carry out rigorous inspections to ensure that all trains are safe for service.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

败选后 黄志明才想起该收紧就业准证?

据了解,全国职工总会秘书长黄志明坦言,针对外籍人士在本地就业,国人的焦虑确有提升,也建议政府或应缩紧就业准证(Employment Pass)政策。 他在前日接受《海峡时报》采访,声称职总就业保障联盟(Job Security Council)迄今协助超过2万工友,在疫情下匹配到新工作。 与此同时,他仍强调建设和扩张新加坡经济牵涉国人利益,仍需要外籍人士的技术和才能,来增强本地劳动力。 他也指若就业竞争某种程度上变得激烈,政府理应出台政策来保障国人能公平地取得好工作。 黄志明原是总理公署部长,在2020选举,偕同原交通部兼卫生部高级政务部长蓝彬明医生、内政部兼卫生部高级政务次长安宁·阿敏等人,上阵盛港集选区,惟不敌工人党何廷儒团队败选。 据了解,在选举之前,黄志明鲜少有提及,有关调整或缩紧外籍人士就业政策的建议。 全国工资理事会将召开第二次会议,黄志明则希望该理事会能尽量保住就业,保障特别是低薪工友群体的福利。 有鉴于冠病疫情对经济的影响,他预计未来半年至一年,失业仍会持续攀升。 职总在上月推出公平裁员框架,并声称保障职场的新加坡核心,惟拥有关键技术的外籍人士也能留下。…

香港今增43冠病确诊!狮城香港航空泡泡证实展延两周

香港今日新增43冠病确诊!有鉴于香港第四波疫情持续加重,香港商务及经济发展局长邱腾华今天(11月21日)召开记者会,证实将新加坡和香港两地的航空泡泡计划,延迟两周,12月初才公布起航日期。 他指双边政府商讨之后,延后两周是较负责任的安排。至于已购买了机票的乘客,航空公司也将会有所安排。 交通部长王乙康稍早前曾表示,计划实行首几天的航班将继续飞,若香港疫情恶化,计划很可能暂停。 他在脸书更新贴文,证实和邱腾华是在今天下午进一步讨论后,作出这项决定。 他称,理解参与计划的旅客会有多失望和沮丧,但从公共卫生的角度出发,这是最好的安排。 民航局今早文告称,香港过去七天日均无关联病例为2.14例。 根据两地协议,若新加坡或香港一周的无关联冠病确诊病例每日平均超过五起,“航空泡泡”将暂停至少两周,直至每日平均少于五起才会恢复。 本月20日,香港新增了26例确诊,是三个月以来的单日确诊最高记录,21例都是本土感染,涉及德士司机、家庭主妇、酒店度宅假和跳舞群组等,一些感染源头不明 然而,仅今日(21日)香港就新增43例确诊,其中多达36起属本土感染,包括13例源头不明的病例。  

垃圾处理公司涉及未采取合理的安全措施 被罚23万新元

垃圾处理公司ECO Special Waste Management(简称,ECO SWM)因两年前大士工业区发生大火,疑似未针对危险废物处理采取合理切实的安全措施,危害员工的而被控违反《工作场所安全及健康法令》第12(1)条,被罚23万新元。 根据人力部周三(28日)文告,火灾于2017年2月23日早上6点10分发生。火灾发生当下,一名ECO SWM的员工正透过柔性金属软管将回收液体己烷(Hexane),从废品储罐中倒入塑料的中间散装容器(Intermediate Bulk Container)。 由于现场还有其他的易燃溶剂,导致火势迅速蔓延,附近的员工也前往现场试图扑灭火势,但无法成功。民防部队在接获通报后赶往救灾,约早上11点,火势得以控制。 据人力部指出,所有员工已被安全撤离,无人伤亡,但其设施却被严重损毁。经调查后,人力部认为ECO SWM所使用的中间散装容器,并不适用于排放己烷所产生的静电作用,导致点燃其蒸气与空气的混合物而引爆。…

【2020财政预算案】明年一月起购电动汽车 可获高达45巴仙回扣

明年一月起,购买全电动汽车和德士的额外注册费,可获得高达45巴仙的回扣。 副总理兼财政部长王瑞杰于国会上公布新财政预算案时宣布,为了到2040年全面淘汰内燃引擎交通工具,政府推出三项方案: 政府将为轻型货车推出“商用车减排税务计划”;而购买全电动的车辆或德士的人士,在缴交”汽车附加注册费”时将享有45巴仙的津贴,最高可获两万元回扣。优惠将从2021年开始落实,为其三年。 将扩大电动汽车充电基础设施,目前我国有1千600个电动车充电点,而我国期望在2030年能够将充电点扩大至2万8千个充电点。 政府带头逐渐开始采购和使用环保交通工具。 王瑞杰说,政府将从明年1月起,在三年内分阶段对电动车辆征收一次性的路税,一些电动汽车车主需缴付的路税会更高,不过由于有了电动汽车附加注册费优惠,车主仍然可以节省一笔费用。 然而,王瑞杰也透露,燃油消费目前为我国带来至少10亿元的收入,但逐渐被电动车取代,因此,电动车辆不需要支付燃油消费税,就需要更新目前的交通税框架。 对此,政府将在明年1月起,为电动汽车征收一次性支付的路税。但距离我国全面采用该新系统仍有几年的差距,因此,政府将在这段过度期间,改以一次性征税的形式来弥补日后所失的燃油税,并于明年1月至2023年1月份段实施,不过,电动车车主仍能通过电动车附加注册费优惠计划,省下不少成本费用。