In the report released by the Auditor-General’s office on July 26, it is made known that the National Arts Council (NAC) which falls under the governance of Ministry of Community, Culture and Youth (MCCY) paid a considerable sum of consultation fees,$0.41 million on a bin centre that cost $0.47 million, without conducting a cost assessment to ascertain the reasonableness of the fee quoted.

In its audit for Financial Year 2015/2016, AGO carried out test checks on six contracts (total contract value of $139.17 million) for the redevelopment of Victoria Theatre and Victoria Concert Hall (VT/VCH) costing $142.86 million, and found two lapses in the management of contract variations.

Inadequate assessment on the reasonableness of the consultancy fee

AGO stated that there had been inadequate assessment on the reasonableness of the consultancy fee of $0.41 million quoted for the construction of a bin centre; the fee was exceptionally high at 87.2 per cent of the construction cost ($0.47 million). Hence, there was no assurance that the fee paid by NAC was reasonable.

AGO observed that NAC had directly engaged the VT/VCH consultants to provide additional consultancy services (amounting to $0.41 million) for the construction of a bin centre, without first conducting a cost assessment to ascertain the reasonableness of the fee quoted.

AGO is of the view that the consultancy fee, at 87.2 per cent of the construction cost of $0.47 million for the bin centre, was exceptionally high.

Based on the terms of reference for this project, NAC was responsible for seeking approval from its tender board for the engagement of consultants. Thereafter, NAC would seek approval for the drawdown of funds from its supervising ministry.

The project was started when NAC was under the then Ministry of Information, Communications and the Arts (MICA) and taken over by the Ministry of Culture, Community and Youth (MCCY) following a restructuring of MICA. AGO noted that when NAC sought approval for the engagement of consultants, it did not carry out due diligence to assess the reasonableness of the consultancy fee.

AGO’s further checks revealed that when approval was sought for the drawdown of funds, the assessment by the then MICA of the consultancy fee quoted was not robust. Instead of using the norm methodology (that is, percentage of the quoted fee over the construction cost of the works) to assess the reasonableness of the fee, MICA had benchmarked the fee for the construction of the bin centre against other more complex projects. Had the norm been used, it would have been clear that the consultancy fee quoted for the bin centre was exceptionally high.

NAC explained that it had worked with its supervising ministry on this project and relied on the ministry’s cost assessment. Going forward, NAC would ensure that the relevant cost assessments are included when seeking approval from its approving authorities for procurement.

MCCY informed AGO that the construction of the bin centre for this project was more complex and required significantly more design expertise, technical consultancy services and effort to coordinate with multiple parties and these were the reasons for the fee to be above the norm.

It acknowledged that the cost assessment could have been more robust.

However, AGO noted that these reasons were not cited in the approval paper for the drawdown of funds and that there was also no documentary evidence that these reasons were indeed considered at the material point in time.

MCCY also informed AGO that it would adopt the norm for cost assessment of consultancy fees for future development projects and provide justifications where there are good grounds for deviation from the norm.

No approval sought for variations (costing $4 million) under two construction contracts 

AGO’s review of 164 variations (amounting to $8.73 million) under two construction contracts revealed 47 variations (estimated at $4 million) that were carried out before approvals were obtained.

The delays in obtaining approval ranged from 12 days to 3.5 years.

In addition, AGO noted that for 38 variations, the approval papers did not highlight that the works had already commenced or were already completed and that covering approvals were being sought. The large number of covering approvals indicated a breakdown in the controls put in place to ensure that variations were properly justified and approved before works commenced. The role of the approving authority was also undermined.

AGO states that the role of the approving authority must not be regarded as perfunctory. If alerted on a timely basis, the approving authority can implement cost control measures to ensure that financial prudence and discipline is maintained. It is therefore important to seek approval on a timely basis and to disclose pertinent facts for approving authorities to make informed decisions.

NAC explained that the lapses were due to the external consultants’ delays in submitting the requests for variation works for NAC’s approval.

Going forward, NAC would put in place measures to ensure that consultants comply with the requirement to obtain approvals before variation works are carried out.

AGO in its remarks on the lapse, noted to NAC that it is accountable for the public funds spent and is responsible for maintaining adequate oversight of the project, including its consultants.

Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
You May Also Like

Singapore to restrict entry for long-term pass holders and short-term visitors with recent travel history to Bangladesh, Nepal, Pakistan and Sri Lanka within last 14 days

The Multi-Ministry Taskforce (MTF) announced on Friday evening (30 Apr) that it…

MOH acknowledges NUH has overlooked patient’s polyclinic referral resulting in overcharging

Last month (21 Dec), a member of the public Ian Lee Chi…

网民质问陈振声 哪来的350万工作机会?

本月19日,贸工部长陈振声透过连线方式,在新加坡峰会发表谈话。 其中,他声称国人无需担心没工作,“在新加坡,我不认为我们会没有工作。我们有250万国人,就职机会有350万个”。 他也提及,技术、经济周期比以往短暂,即便电脑科学毕业,五到10年后又需要学习新技术,这致使我们必须不断学习适应新局势。故此挑战不在于抗拒数码化或全球化,而是如何让国人做好不断应对变化的准备。 因疫情一些白领工作转到居家工作后,人们发现一些工作因网络便利已不受地理限制,而更具竞争性。这使得白领群体更需要终身学习,确保保持竞争力找到工作。 他认为,尽管自动化、数码化对新加坡更有利,但挑战也包括如何让那些受到数码化影响的人们,重新装备新技术以参与新的经济模式。 然而,并非所有网民都认同他的言论,对于用350万个就业机会言论持怀疑态度。特别是所谓350万份工作,是否也包括了清洁工、保安、德士司机等非高技术职缺?网民表示,人民都要打两份工才能温饱,有些工作的薪金根本无法应付本地开销。 350万份工作有哪些?网民愿闻其详 例如Kenneth Ong就问道,这些350万份工作机会有哪些?是否能开诚布公让民众检视? 此外,网民对于居家工作一事也有意见,认为陈振声的说辞不合理,因为事实上并非所有人都可以回到母国工作。“若是真的,那么可以把办公室转移到更低成本的国家。” “那么将新印全面经济合作协定(CECA)带来的外籍专才送回他们的国家,让他们赚取自己国家的钱币,毕竟我国的汇率更高。” 网民也认为我国在数码化方面已经落后很多国家,其他国家如印度、韩国、日本和美国都遥遥领先,才导致我国一直要“输入”外籍人才。因此我国大学应该尽早专注于电脑和数码科技的研究及学习。

Reactions to the the expulsion of Dr Poh Lee Guan from the Workers' Party

~by Cheong Yaoming~ Dr Poh Lee Guan, a long serving Council Member…